We’re proud to report that the construction of Port Lane is underway. To keep up to date on its progress, register your interest to have updates sent straight to your inbox.
Townhome Construction:
Stage 2
Townhomes 96 – 103
Estimated Completion – August – September 2025
65%
Townhome Construction65%
Base100%
Frame100%
Lock-up85%
Fix40%
Completion0%
Stage 3
Townhomes 25 – 28
Estimated Completion – June 2025
96%
Townhome Construction96%
Base100%
Frame100%
Lock-up100%
Fix99%
Completion80%
Stage 3a
Townhomes 29 – 33
Estimated Completion – June – July 2025
87%
Townhome Construction87%
Base100%
Frame100%
Lock-up100%
Fix92%
Completion45%
Stage 4
Townhomes 34 – 42
Estimated Completion – August 2025
65%
Townhome Construction65%
Base100%
Frame100%
Lock-up90%
Fix35%
Completion0%
Stage 5
Townhomes 43 – 50
Estimated Completion – July – August 2025
65%
Townhome Construction65%
Base100%
Frame100%
Lock-up90%
Fix35%
Completion0%
Stage 6
Townhomes 51 – 55
Estimated Completion – July – August 2025
65%
Townhome Construction65%
Base100%
Frame100%
Lock-up90%
Fix35%
Completion0%
Stage 7
Townhomes 104 – 107
Estimated Completion – August – September 2025
58%
Townhome Construction58%
Base100%
Frame100%
Lock-up70%
Fix20%
Completion0%
Stage 8
Townhomes 108 – 117
Estimated Completion – August – September 2025
56%
Townhome Construction56%
Base100%
Frame100%
Lock-up60%
Fix20%
Completion0%
Stage 9
Townhomes 56 – 63
Estimated Completion – August – September 2025
53%
Townhome Construction53%
Base100%
Frame100%
Lock-up65%
Fix0%
Completion0%
Stage 10
Townhomes 72 – 81
Estimated Completion – June – July 2025
78%
Townhome Construction78%
Base100%
Frame100%
Lock-up100%
Fix92%
Completion0%
Stage 11
Townhomes 64 – 71
Estimated Completion – August 2025
54%
Townhome Construction54%
Base100%
Frame100%
Lock-up70%
Fix0%
Completion0%
Stage 12
Townhomes 82 – 87, 120 – 122
Estimated Completion – June – July 2025
78%
Townhome Construction78%
Base100%
Frame100%
Lock-up100%
Fix92%
Completion0%
Stage 15
Townhomes 88 – 95, 118 – 119
Estimated Completion – August – September 2025
58%
Townhome Construction58%
Base100%
Frame100%
Lock-up70%
Fix20%
Completion0%
Completed:
Stage 1
Townhomes 16 – 24
Completed – April 2025
Stage 14
Townhomes 1 – 7
Completed – May 2025
Stage 16
Townhomes 8 – 13
Completed – May 2025
Stage 17
Townhomes 14 – 15
Completed – May 2025
* Estimated construction dates are provided as an approximate guide only and are subject to change. The date estimates provided are based on current information regarding the design, construction, and relevant authority approvals timeframes for the individual stage. Port Lane uses this information to provide an estimate of the month (or month/quarter ranges) in which titles will be achieved however this is subject to change and is often influenced by factors which are often outside of the projects control such as weather, contractor delays and authority inspections.